Long-Term Load Forecasting Using Neural Network Technique for Distribution Substation System Expansion Planning (Case Study: Debre Work Town)
Loading...
Date
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
ASTU
Abstract
Load forecasting is the prediction of demand for the next period and is an essential
requirement for new planning and expansion planning of power systems. Knowing the future
demand in concise way has been still a big problem in Ethiopia to meet the power demand
for different load types like industrial, commercial, city municipal services or public services,
agricultural and domestic services. In this thesis, load forecast for Debre Work town and
its surrounding has been obtained for the period of 2023 to 2037 and distribution substation
system expansion planning model has been planned with technical feasibility study, which
has covered load flow analysis, contingency analysis and short circuit analysis to meet the
forecasted load . The following independent variables have considered, namely - GDP,
number of populations, GDP/CAP, weather conditions like temperature and electricity
consumption by the people (EP) as the factors that affecting the future load growth in Debre
Work town. MATLAB software has been used for training and testing for the general neural
network techniques such as LSTM-RNN and GRU-RNN. LSTM-RNN result was better than
GRU-RNN in good fitting from assessment measurement parameters results. From training
time view point, GRU-RNN was better than LSTM-RNN. However, LSTM-RNN has selected
for this thesis because the training time difference was not that much big. PSSE (power
system simulator for engineers) software has been used for distribution substation system
expansion planning model to simulate and test the network feasibility. After forecasting the
future load demand of Debre Work town, new distribution substation system expansion
planning model has been applied to meet the forecasted power demand and testing of
network technical feasibility and these analyses has meet the requirements of technical
feasibility analysis limit of EEA/2022 standards. The thesis has also studied the cost of the
substation and transmission line from LILO point to Debre Work substation which was
528,653,214 Ethiopian Birr currently. Generally, load forecasting for Debre Work area has
been done and comparison of forecasting techniques such as LSTM and GRU has been
conducted and even their result has shown almost similar, LSTM result was good, modeling
of distribution substation has been done and finally substation cost estimation was done.