Evaluation of Kumkang Aluminum Formwork Performance in Federal Housing Corporation Projects
Loading...
Date
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
ASTU
Abstract
Due to the rapid population growth and urbanization in Ethiopia over the past decades, there
is a shortage of affordable standard housing projects in all towns. To meet the requirements of
more housing projects in a short period, the construction firm is in charge of selecting proper
formwork material, but one of the major constraints for the timely completion of the housing
projects are the formwork used by the company. Conventional formwork construction system
in Ethiopia takes relatively longer time to construct, add cost to the project, reduce productivity
and quality of concrete surface mostly not good. Thus, the objective of this study is to evaluate
the kumkang aluminum formwork performance in federal housing corporation projects. In
order to achieve the research objectives, this study targets the total ongoing projects which are
owned by federal housing corporation in Addis Ababa city. Due to less number of ongoing
projects and the form work system which is applied by one of federal housing projects, the
census sampling method was used. The data were collected through a combination of
interviews, questionnaires, and case studies. There were 75 questionnaires distributed in all
ongoing federal housing projects and 61(81.3%.) were returned and for purpose of the
interview, 20 different professional respondents were taken. The data collected by quantitative
method were analyzed using statistical package for social science and Microsoft Excel 2007
and Origin pro used for supporting the data analysis and present through Frequency tables,
percentages, bar charts, and other descriptive measurements. Qualitative data which is
interview also analyses differently and present in a combination of quantitative data. The case
studies comparison was present by using tables and graphs. The study result indicates that the
kumkang formwork system can construct through manually by unskilled labour and the
formwork costs less than wooden formworks, it saves almost 173.29 Birr/m
2
or 40% of
formwork cost in construction is reduced by using Kumkang Aluminium formwork. In terms of
time, 7 days utilized to construct one-floor formwork by kumkang including formwork strip,
while the conventional formwork takes 21 to 31 days for erection only. This implies a 3- 4 floor
formwork construction time in kumkang aluminum formwork and the Kumkang Aluminum
formwork have improvements on conventional formworks with greater than 60% in all quality
of finished concrete measurements. The kumkang aluminum formwork have less risk and better
safety during construction in the aspect of health and safety factors. The Kumkang Aluminium
formwork is also beneficial for enhancing sustainable construction. Nearly all of the
sustainable formwork system elements are fulfilled by this formwork. The productivity of labour
in Kumkang Aluminum formwork have an improvement with 0.91, 3.61, 4.59 m2
/hr. for stair,
wall and floor slab respectively in formwork erection than in wooden formwork and during
formwork stripping the productivity of labour in kumkang formwork enhance the wooden
formwork by 0.85, 5.18, 5.95 m2
/hr. in a stair, wall, and floor slab respectively and the monthly
progress of labour productivity was increase from month to month in kumkang aluminum
formwork but, the reverse in the case of wooden formwork. From the findings of this study, it
can be generalized that the kumkang aluminum formwork have a great advantage and better
performance with regard to minimize the cost of construction, speed the construction time, good
quality of finished concrete, safer construction environment, enhancing sustainable
construction, and increasing labour productivity. As an initial study on the performance of
kumkang aluminum formwork, further and more detailed studies should be conducted on such
formwork system application, construction methodology, design, and formwork management.